Albion Tower
Leeds

Approx Services Value: £2,000,000

Construction Period: 9 months

Project Description: FHP Partnership were appointed by Tops Shop Estates plc to design the mechanical and electrical services associated with the complete refurbishment of the top three floors of office accommodation, complete with total replacement of curtain walling system, and renewal of all central plant and distribution systems, etc, with existing tenants remaining in-situ on lower four floors of the building.

All existing services to lower floors to be kept fully operational throughout the installation of the new systems.

Services Provided:
Comfort Cooling via 4-pipe Chilled Beams including new chiller, dry coolers and chilled water distribution system
New LPHW boilers and perimeter heating, via trench heating
Domestic Hot and Cold Water Services
Supply and extract Ventilation
Toilet Extract
Above Ground Drainage
BMS
Mains Switchgear
Lighting & Emergency Lighting
Small Power and Fire Alarms
Security Installation
Telephone/Data Containment
Lightning Protection
External Feature Lighting